JUST IN: Federal Government offered Julius Berger fresh N20.5bn to complete Bodo-Bonny Road Project

The Federal Government has offered additional N20.5 billion to construction giant, Julius Berger to complete the Bodo-Bonny Road even as it sets December 2024 deadline to complete the project or face termination....READ FULL ARTICLE

Minister of Works, Engr. David Umahi gave the deadline and made the offer on Wednesday during a meeting with contractors and the peace committee on the project from Bonny Kingdom, in Abuja.

The project was awarded to Julius Berger at the cost of N120.6 billion with 50 per cent funding by the Nigeria LNG Limited (NLNG).

Related Post  BREAKING: 44-Year-Old Former Bank Employee, Mike Ilishebo Kills Wife Before Taking Own Life

Berger had demanded additional N28.8billion to construct the remaining section of the 39 km road which is currently at 84 percent completion phase.

The construction firm, among other conditions, made the additional demand following foreign exchange rates.

The federal government had however offered N13 billion earlier leaving with a difference of N15 billion but after further negotiation, the minister increased the offer to N20 billion for Julius Berger to accept or quit the site.

Related Post  Netizens Outraged As Viral Video Exposes Alleged R@pe Of A Minor By Reno Omokri’s Step-Brother, Sparks Controversy (WATCH)

Umahi however promised to ensure the completion of the work by December 2024.

The 39 km long road, has cross culverts and two mini bridges with a distance of 23m each as well as two creek bridges at Afa Creek Bridge of about 530m length and Nanabie Creek Bridge of about 640m length.

This is in addition to the construction of a major river bridge of about 750m length over the Opobo Channel.

Related Post  BREAKING: Gunmen Brutally Murder Two Brothers, Nursing Mother And Newborn Baby In Cold Blood

The minister had declined the construction firm’s fresh requests, warning that the ministry would not allow contractors to dictate for Nigeria.

He said the ministry under his watch will not sign contract variations based on foreign exchange rates. He also said the ministry has stopped payment of VOPs unless directed by the President....READ FULL ARTICLE